Current Temperature
3.6°C
By Heather Cameron
Taber Times
Local Journalism Initiative Reporter
During a recent M.D. of Taber Council meeting, Council discussed awarding the tender for Phase 3 of the Horsefly Regional Emergency Spillway.
Arlos Crofts, Chief Administrative Officer for the M.D. of Taber, explained to Council that the tender closed on September 20 and there were four tenders submitted with GST excluded. The tenders were from Degraaf Excavating Ltd. for $6,944,664.50; Whissel Contracting Ltd. for $7,517,400.35; BYZ Enterprises Inc. for $7,898,000; and Bullin Construction Co Ltd. for $7,994,859.
Crofts stated that the recommendation was that the M.D. of Taber, as managing partner for the Southern Regional Storm Water Drainage Committee, award the tender for Phase 3 of the Horsefly Regional Emergency Spillway to the lowest bidder, Degraaf Excavating Ltd., for the tender amount of $6,944,644.50 (GST excluded).
Ultimately, a motion was made and was carried.
“I think this is a testament to the Administrative team on the last phase in getting 22 contractors out to do the pre-site visit,” said Councillor John Turcato. “I think that’s huge, and as we can see by the tender results, I think that also bodes well for our management of these projects.”
You must be logged in to post a comment.